Bunge: migration from Quantum/Premium to Siemens PCS 7

Approximately 4,000 I/O and an on-site intervention concentrated in a one-month shutdown. A complete MIESA turnkey project: the plant runs on the new Siemens PCS 7 system and MIESA continues to carry out its maintenance.

Client
BUNGE
Year
2025
Area
Control system modernisation and migration
Subsector
OILSEEDS AND VEGETABLE OILS

Scope

Migration of the control system of a Bunge plant from the old Schneider Quantum and Premium PLCs to Siemens PCS 7: around 4,000 I/O signals, more than 50 drives and starters replaced, new motor current signals, as-built documentation of the installation and a one-month shutdown with 49 people on site.

  • ~4,000I/O signals within the migration scope
  • 100%of the plant’s loads rewired
  • 50+drives and starters replaced
  • 49people on site at the same time during the one-month shutdown

From the old PLCs to PCS 7

The plant was controlled by Schneider Quantum and Premium PLCs. The project replaced those PLCs with a Siemens PCS 7 distributed control system, with a scope of approximately 4,000 input and output signals.

  • Migration of control from the Schneider Quantum and Premium PLCs to Siemens PCS 7
  • Rewiring of 100% of the plant’s loads
  • Replacement of more than 50 drives and starters
  • Addition of motor current signals
  • As-built documentation of the installation: updated records of the plant’s real condition

MIESA’s scope: a complete turnkey project

MIESA delivered the project on a turnkey basis, from start to finish, with its own resources:

  • As-built survey of the existing installation
  • Construction of the cabinets in our workshop
  • On-site installation
  • Programming of the new PCS 7 system
  • 24/7 support during start-up
  • Maintenance of the installation, which we still carry out today
Cabinet of the new PCS 7 system: controllers, switches and communications
Cabinet of the new PCS 7 system: controllers, switches and communications
Rewired ET 200SP HA I/O
Rewired ET 200SP HA I/O
Control and I/O cabinet
Control and I/O cabinet
Replaced variable speed drives
Replaced variable speed drives
Soft starters
Soft starters

Motor current monitoring

The project also added motor current signals, measured with Rogowski coils on the motor feeders, so that this information is available in the control system.

Rogowski coils for motor current measurement on the motor feeders
Rogowski coils for motor current measurement on the motor feeders
Terminal blocks and signal wiring
Terminal blocks and signal wiring

Target architecture

The new system is based on Siemens PCS 7 with distributed I/O in the plant’s two areas: 20 ET 200SP HA stations and 12 ET 200iSP PN stations, the latter in the extraction area.

Preparation

  • 16 ET 200SP HA stations

Extraction

  • 4 ET 200SP HA stations
  • 12 ET 200iSP PN stations

Organising the work: the 2025 shutdown

The project totalled around 26,300 working hours and was delivered in less than a year. The on-site intervention was concentrated in a one-month shutdown, during which installation, programming, testing and commissioning were carried out at the same time; that month does not include the prior preparation or the engineering and programming done at our facilities.

  1. 01

    Before the shutdown

    Field data collection and pre-installation of cable trays and cables, so everything is ready for the shutdown.

    4,694 h13 people

  2. 02

    Engineering and workshop at MIESA

    Programming, engineering, drafting and manufacturing at our facilities, in parallel with pre-installation.

    12,569 h14 people + workshop

  3. 03

    During the shutdown

    A one-month shutdown: installation, programming, testing and commissioning at once, with engineers and instrument technicians on site.

    9,081 h49 people on site

Hours by discipline: programming 10,828 h (41%), installation 7,997 h (30%), engineering 6,926 h (26%) and workshop 592 h (2%).

Panel work during the shutdown
Panel work during the shutdown
Rewiring of an I/O box in the field
Rewiring of an I/O box in the field
I/O box during rewiring
I/O box during rewiring

Simulation with SIMIT and operator training

Before working on site we used SIMIT to test the programming of the new system. The same model was used as an OTS (Operator Training System), so that operators could learn to run the plant with the new control system before commissioning.

See the SIMIT simulation and OTS project →

Testing and control of the intervention

  • Input and output (I/O) checks
  • Communications checks
  • Sequence and interlock testing
  • Verification of equipment operation
  • Daily monitoring of the work, meeting the customer’s requirements

Result

The plant runs on the new Siemens PCS 7 system and MIESA continues to carry out the maintenance of the installation.

Industrial maintenance →

More about this service: Control system modernisation and migration →

  • Schneider Quantum
  • Schneider Premium
  • Siemens PCS 7
  • ET 200SP HA
  • ET 200iSP
  • Variable speed drives
  • Rogowski coils
  • Motor current signals
  • As-built
  • Migration
  • 4,000 I/O